Well, the rain held off through Monday and Tuesday so we got some work done. But Wednesday was so nasty we left soon after lunch. The trusses are up on # 4 with bird blocks, some fascia and gable OSB. All of the walls are done except for the narrow ones at the front of the garage.
The cupboard blocking is up in all four houses and some of the lid backing (otherwise known as sheet rock nailer) is up in number 6.
Trusses and bird blocks are up on # 14 and # 6. The conditions were lousy but our currently-at-liberty framers did a great job. We really benefit from their being available, but we sincerely hope they will soon be too busy to help us.
It was a wet sloppy week with mud and mist, but also with the great fun of being back together and back at work after the holidays.