Thursday, January 14, 2010 @ 2:20:00 PM - Written by Ann Kelly
The regular crew only worked Monday and Wednesday this week. J Bar J came on Tuesday and worked on the Youth Build. Hopefully the second half of the week will be drier. Still we got a lot done.
All four of the houses are at about the same stage of completeness. Trusses are pretty much set; fascia is about half on and pretty board is well under way. OSB - under siding - is on everything except the second floor of # 8. There is some blue board - sheet insulation - on # 6. Soon we will have a dry place to work on rainy days.
All four of the houses are at about the same stage of completeness. Trusses are pretty much set; fascia is about half on and pretty board is well under way. OSB - under siding - is on everything except the second floor of # 8. There is some blue board - sheet insulation - on # 6. Soon we will have a dry place to work on rainy days.