What a muddy week. But it was a 2-day week for us with a snow-day on Tuesday. Still, we made progress.
# 14 has its fascia and is, I think, fully sheathed. #8 has trusses on the garage and is partially covered with blue board. Neither the roof nor the second floor is sheathed. Some corner trim is done on # 6, and most of the windows are in, some of them trimmed. We ran the laser transit around to get started doing all the siding level. The plumber was poking holes in the roof sheathing.
The roof of # 4 is almost completely sheathed. It is not a good idea to try to sheath with icy OSB, so we couldn't finish that one.
We expect a large group to work on the Faith Build, # 8, this Saturday. I expect there will be a noticeable increase in wall sheathing and blue board there. Maybe they will set the trusses on the main part of the house.
It was a week of incremental progress and satisfying in a low key way.